Self-build home: Appoint a contractor to construct the home
Preparing tender documents.
Before appointing a contractor to construct the home, it is important to decide:
- The form of contract and contract conditions.
- Requirements for contractual warranties and performance bonds.
- Works that will not be part of the contract.
- The dates for commencing and completing the works and any phasing requirements.
The designer should co-ordinate the preparation of tender documentation, a pre-tender estimate (the final estimate of the likely cost of the works) and a cash flow projection (so that the requirement for funds is known).
The tender documentation provides a detailed description of the works that is issued to prospective contractors (tenderers) so they can prepare an offer (tender) for carrying out the works.
The tender documents might include:
- A letter of invitation to tender.
- The form of the tender submission that is required from prospective contractors. The more prescriptive this is about what is required, the easier it will be to compare tenders from different prospective contractors.
- Preliminaries. A description of the project that allows the contractor to assess costs which, whilst they do not form a part of any package of works, are required by the method and circumstances of the works, such as; contractors site huts, site hoardings, scaffolding, site plant and so on.
- The form of contract and contract conditions.
- The tender pricing document. Effectively this is an unpriced bill of quantities onto which contractors enter the prices, rates and totals that constitute their offer. Requiring contractor's to present their offer in this way makes it easier to compare submissions by different contractors. It can also help negotiations, by allowing easy identification of areas where one contractor may be proposing to charge significantly more than another.
- Design drawings.
- Specifications.
Selecting a contractor.
Potential contractors might be identified by:
- Advertising.
- Research.
- Recommendation.
- Existing relationships.
Interviews might then be carried out to produce a short list that appear suitably experienced, available and easy to work with.
The designer collates the tender documents and arranges dispatch to and return from the tenderers. It may be appropriate to arrange mid-tender interviews for the tenderers to answer questions, talk through alternative proposals, and to arrange site visits.
The designer co-ordinates assessment of the tenders received from contractors and may conduct further interviews. The designer prepares a tender appraisal report and negotiations are entered into with the preferred tenderer. A reserve tenderer may be selected in the event that negotiations are unsuccessful.
Before a decision is made to appoint the preferred tenderer, it is important to ensure adequate funding is in place.
The designer collates the contract documents and arranges for the execution of two copies, one for the self builder and one for the contractor. The contractor may be required to provide evidence of their insurance cover.
NB Self-build clients are ‘domestic clients’ for the purposes of the Construction (Design and Management) Regulations (health and safety regulations generally referred to as the 'CDM Regulations'), and so the client's duties under the regulations will generally fall to the contractor. See CDM for self-builders and domestic clients for more information.
Featured articles and news
The term value when assessing the viability of developments
Consultation on the compulsory purchase process, compensation reforms and potential removal of hope value.
Trees are part of the history of how places have developed.
The increasing costs of repair and remediation
Highlighted by regulator of social housing, as acceleration plan continues.
Free topic guide on mould in buildings
The new TG 26/2024 published by BSRIA.
Greater control for LAs over private rental selective licensing
A brief explanation of changes with the NRLA response.
Practice costs for architectural technologists
Salary standards and working out what you’re worth.
The Health and Safety Executive at 50
And over 200 years of Operational Safety and Health.
Thermal imaging surveys a brief intro
Thermal Imaging of Buildings; a pocket guide BG 72/2017.
Internally insulating a historical building
An experimental DIY approach using mineral thermal lime plaster.
Tree species selection for green infrastructure: A guide for specifiers.
50 million new trees over 25 years.
Art of Building CIOB photographic competition public vote
The last week to vote for a winner until 10 January 2025.
The future of the Grenfell Tower site
Principles, promises, recommendations and a decision expected in February 2025.
20 years of the Chartered Environmentalist
If not now, when?
Journeys in Industrious England
Thomas Baskerville’s expeditions in the 1600s.
Top 25 Building Safety Wiki articles of 2024
Take a look what most people have been reading about.
Life and death at Highgate Cemetery
Balancing burials and tourism.
The 25 most read articles on DB for 2024
Design portion to procurement route and all between.